No need for extra time with pre-sealed ductwork

Published:  08 November, 2006

Doncaster
Savings in installation time of over 40% for LindabSafe pre-sealed ducting have helped ensure that the new stadium of Doncaster Rovers FC did not incur the penalties of extra time.

The speed of installation of LindabSafe ductwork in the new stadium of Doncaster Rovers has helped reduce the risk of the project moving into extra time.

As part of the fit-out of the stadium at the 32 million Lakeside Sports Complex, around 6.5 km of LindabSafe ductwork and fittings in diameters from 100 to 500 mm has been installed in kitchens, washrooms, conference facilities and hospitality areas.

The Lindab products were specified and installed by DuctVent Services of Bolton. Sam Taylor, a director of the company explains that these products are quick and easy to install because the factory-fitted gaskets mean sections can simply be pushed together to create a highly airtight seal.

He says, We chose LindabSafe because of the amount of time we save, and thanks to that we are ahead of schedule. Lindab says that LindabSafe saves at least 39% on installation time, and in our experience, that is about right.



comments powered by Disqus

Search

Welcome

Welcome to Modern Building Services Online, the web edition of Modern Building Services (MBS) journal and the UK's most popular Building Services engineering site. Modern Building Services covers the entire Building Services Engineering industry. This site contains archived content from the journal, plus web-specific content.

When you go to our digital edition, you can also access the archive of digital editions.
June 2018: DIGITAL EDITION

ARCHIVE OF DIGITAL EDITIONS

Modern Building services has a group
on Linkedin - join us!

Jobs

  • Energy and sustainability: Performance and analysis manager

     An exciting opportunity will arise shortly for an exceptional person with extensive experience of managing sustainability within large complex organisations. Can you demonstrate extensive experience of energy management, proven ability to drive program......

more jobs »

Poll

"Is the Building Services industry lagging behind in the implementation of BIM?"



Calendar