Keysource completes data centre in record time with modular off-site construction

Keysource, data centre

Keysource has completed a 100 m2 data centre for Jaguar Land Rover’s new engine-manufacturing centre in Wolverhampton. A power usage effectiveness (PUE L2YC) of better than 1.2 has been achieved by using variable-speed fans positioned so that hot and cold air are separated via the wall rather than under the floor.

This core data centre houses 30 racks with a capacity of 320 kW. It provides critical power through an N+1 UPS system and 2N standby diesel generators. The power module was designed and built offsite and offers scalability to support future expansion.

Andy Hayes, director with Keysource, explains, ‘Using a modular design means that the bulk of production and preparation can be done off site, which reduces costs and saves time.

‘Typically, a project of this nature would take at least 12 months to complete, but using modular designs reduced this by two thirds.

‘Along with our cooling-efficiency design measures, we can see this modular approach as a template for future data centres.’

Related links:
Related articles:



modbs tv logo

First keynote speakers announced by Europump

The first two keynote speakers have been announced for an annual event being hosted by the British Pump Manufacturers Association (BPMA).

‘Landmark’ prosecution of online seller welcomed by REFCOM

The air conditioning and refrigeration industry’s largest safety register REFCOM has welcomed the successful prosecution of online sales company Appliances Direct (AD) for breaching F-Gas Regulations.